B. Com. (Bachelor of Commerce)
3rd Semester
Cost Accounting
BCM-302
Time allowed: 3 Hours][Max. Marks: 80
NOTE: Attempt four short answer type questions from Section A carries 5 marks each. Attempt two questions each from Section B and C respectively carries 15 mark each.
Section A
1) Difference between Bin Card and Stores Ledger.
2) What is overtime time. Discuss its accounting treatment?
3) From the following information calculate the cost for the month of October
4) Mr Munnabhai furnishes the following data relating to the manufacture of a standard product during the month of April 2011.Raw Material Used Rs. 15,000; Direct Labour Charges Rs. 9,000; Machine Hours worked 900 Hours; Machine Hour Rate Rs. 5; Administrative overhead 20% works Cost
Selling Overheads Rs 0.50 per unit; Units produced 17,100 units; Units Sold 16,000 Units @ Rs 4 Per Unit
You are required to prepare Cost sheet from the above Showing
(a) Cost of production per unit
(b) Profit per unit sold and profit for the period
5) A company manufactures table fans, ceiling fans, and room coolers. The materials and wages cost are as under:
Total factory overheads Rs. 55,000. You are required to determine the works cost of each type of furniture after assuming that one ceiling fan is equivalent to two table fans and one room cooler is equal to five table fans for the purpose of factory overheads allocation.
6) From the following transactions, prepare Stores Ledger using the suitable method.
January 01 Opening balance-200 units @ Rs. 6 per unit
January 05 purchases- 400 units @ Rs. 7 per unit
January 20 Issue- 200
February 05 issue- 100 units
February 06 purchases- 800 units @ Rs. 8 per unit
February 10 issue- 200 units
February 12 issue- 150 units
Section B
7) Compute the Machine Hour Rate from the following data:
The Machine occupies of the total area of the shop. The Supervisor is expected to devote 1/5th of his time for supervising the machine.
8) From the following particulars, you are required to work out the earnings of a worker under:
straight piece rate system; (b) differential piece rate system; (c) Halsey Premium Plan (50%) bonus; (d) Rowan Plan.
12) In a factory there are two service departments S1 and S2 and three production departments P1, P2 and P3. In April 2021 the departmental expenses were: